RIBA ยท Project Planning
Project Timeline Estimator
Estimate project duration across RIBA Plan of Work stages with a Gantt-style timeline view.
Project Type
Project Scale
Estimated Timeline
โSelect project type and scale
Notes
- Stages can overlap โ real programmes are typically 15-20% shorter
- Planning determination takes 8-13 weeks (not included in design stages)
- Construction duration varies hugely by procurement route and site
- Add contingency of 10-15% to overall programme
RIBA Plan of Work 2020
0 Strategic Definition 2โ4 wks
1 Preparation & Briefing 4โ8 wks
2 Concept Design 6โ12 wks
3 Spatial Coordination 6โ12 wks
4 Technical Design 8โ16 wks
โ Planning Application 8โ13 wks
5 Construction Varies wks
6 Handover 2โ4 wks
Construction Duration
Small (<500 mยฒ): 6โ12 months
Medium (500โ2000 mยฒ): 12โ18 months
Large (2000โ5000 mยฒ): 18โ30 months
Very large (>5000 mยฒ): 24โ48 months