RIBA ยท Project Planning

Project Timeline Estimator

Estimate project duration across RIBA Plan of Work stages with a Gantt-style timeline view.

Project Type

Project Scale

Estimated Timeline

โ€”

Select project type and scale

Notes

  • Stages can overlap โ€” real programmes are typically 15-20% shorter
  • Planning determination takes 8-13 weeks (not included in design stages)
  • Construction duration varies hugely by procurement route and site
  • Add contingency of 10-15% to overall programme

RIBA Plan of Work 2020

0 Strategic Definition 2โ€“4 wks
1 Preparation & Briefing 4โ€“8 wks
2 Concept Design 6โ€“12 wks
3 Spatial Coordination 6โ€“12 wks
4 Technical Design 8โ€“16 wks
โ€” Planning Application 8โ€“13 wks
5 Construction Varies wks
6 Handover 2โ€“4 wks

Construction Duration

Small (<500 mยฒ): 6โ€“12 months

Medium (500โ€“2000 mยฒ): 12โ€“18 months

Large (2000โ€“5000 mยฒ): 18โ€“30 months

Very large (>5000 mยฒ): 24โ€“48 months